Project Timeline
Status Legend
| Completed. | |
| Within 48 hours of being completed, given committee approval. | |
| Completion is dependent on receipt of content and committee approval. |
Project Status Timeline
Phase |
Project |
Status |
Completion Date |
One |
Template for website | Done |
Wednesday, December 20th, 2007 |
domain name registration (http://www.4As. us) |
Done |
Monday, |
|
| Web hosting plan established with http://www.hostingleader.com | In work. Waiting for receipt of $275 fee for one year's hosting. Will contact Mr. Larkin for more information |
Planned completion date: Thursday, |
|
| Membership Information | In work. Need to convert existing affiliate application to PDF |
Planned completion date: Thursday, |
|
| Membership Directory | In work. Awaiting discussion with Marvin Perry and additional content. |
TBD |
|
About Us page 4a History |
In work. Awaiting additional content and committee approval |
TBD |
|
| Committee page | In work. Awaiting additional content and committee approval |
TBD |
|
News & Events Calendar page Calendar of Events |
In work. Awaiting additional content and committee approval of calendaring system. Cost: $49 |
TBD |
|
Organizational Page Officers |
In work. Awaiting additional content and committee approval |
TBD |
|
| Phase One, unveiling of website | Needs: 1. Content |
Planned launch date: March 1st, 2007 |
|
Two |
Listserv of 4A membership | In work. Awaiting discussion with Marvin Perry and Committee Approval of policy and procedure |
|
| Photo Gallery | Discussion needed | ||
| Streaming Video | Discussion needed | ||
| Search Utility | Discussion needed | ||